Essay Available:
page:
6 pages/≈1650 words
Sources:
1
Style:
Harvard
Subject:
Management
Type:
Coursework
Language:
English (U.S.)
Document:
MS Word
Date:
Total cost:
$ 31.1
Topic:
Project Management
Coursework Instructions:
some quesitons need to be calculated
Coursework Sample Content Preview:
PROJECT MANAGEMENT
The Name of the Class (Course)
Professor (Tutor)
The Name of the School (University)
The City and State where it is located
The Date
Question 1
Earned value analysis
1 SPI
The schedule performance index measures the efficiency of time utilization on a project. This can be done by
SPI=EVPV
EV, also known as the earned value, is the value of the actual work performed at a specific time. This can be determined by
EV= 4270× £150000= £90000
On the other hand, the planned value, which is the value of the work planned to be performed at a specific point in time, can be determined by
PV=3550×15000= £105000
Therefore, SPI =EVPV= 90000105000
Therefore, SPI= 0.85
2 Cost Performance Index CPI
The cost performance index (CPI) is defined as the efficiency measure of cost utilization on a project. It can be determined by dividing the earned value by the actual cost.
CPI = EVAC
For this case, the actual cost of the work performed is £90000
Therefore, CPI =£90000£90000=1.0
3 Estimate to Completion (ETC)
Estimate to completion is the cost required to finish the project. ETC can be determined as follows
ETC=(BAC-EV)CPI
The total budget of completion, also known as BAC for the project, is £150000
Therefore, ETC= £150000-900001.0= £60000
4 Estimate at completion (EAT)
Estimate at completion can be determined as follows
EAC=BACCPI
Thus,
EAC150,0001.0=150000
Additionally, the estimated completion estimate can be determined by adding the actual cost to the estimated completion estimate. For instance, EAC= AC+ ETC
Thus, 90,000+60000= 150000
5 Variance at completion VAC
The variance at completion can be defined as the difference between the budget at completion and the Estimate at completion. Various methods can be used to calculate the variance at completion.
VAC= BAC -AEC
Therefore,
VAC = 150000-150000=0
It can also be determined as follows
VAC= BAC-EAC
Thus, VAC = 150000-150000=0
The revised duration for the project is calculated as follows,
Planned duration/ SPI
Thus
Revised duration= 50/ 0.0857= 58.36 weeks
Project Status
According to the conclusion drawn from Earned Value Management, the project is out of schedule and on budget.
Conclusion:
There is also evidence of delay under the specific performance index since the SPI is 0. 857, meaning the project has been delayed. However, price-wise, it sits within the completion with a calculated CPI of 1. 0. The estimated time required for the project has now been adjusted to take approximately 58. 36weeks.
1 Decision Tree Analysis for Office Building Design
Two alternative designs (Design A and Design B) are considered for the architectural scheme of an office building:
* Design A:
...
Get the Whole Paper!
Not exactly what you need?
Do you need a custom essay? Order right now:
👀 Other Visitors are Viewing These APA Essay Samples:
-
Fundamentals of project management
7 pages/≈1925 words | 6 Sources | Harvard | Management | Coursework |
-
NEW CPP & DEADLINE A new brand: Elysian Intimates
5 pages/≈1375 words | 20 Sources | Harvard | Management | Coursework |
-
organisational development
14 pages/≈3850 words | No Sources | Harvard | Management | Coursework |